Vita Load Navigator at Chapter Living

  • Project: Chapter Living
  • Location: London
  • Client: Mace

Project Overview

WOLFF Onsite is proud to share a glimpse into the Chapter Living project, where the Vita Load Navigator (VLN) played a pivotal role in overcoming on-site challenges. This project, which began in 2023, involves the construction of a state-of-the-art student accommodation tower in the heart of London.

Challenges

Working with Mace, the project's main contractor, WOLFFKRAN supplied tower cranes strategically positioned on grillages, due to the tight and constrained urban environment. Building in central London often presents logistical challenges, and this site was no exception. With limited space for manoeuvring materials and unpredictable UK weather conditions, maintaining progress required innovative solutions.

The Solution

Recognising these hurdles, WOLFF Onsite introduced the Vita Load Navigator to the project. This device provided an essential advantage, allowing for faster and more efficient material installations. By stabilising loads in real-time and counteracting wind-induced rotation, the VLN ensured that progress remained on track - even during windy conditions.

Provided by WOLFF Onsite:

Vita Load Navigator

Features:

  • Stabilise, control and precisely place lifts of up to 40MT
  • Holds a user set position in a wind gust of up to 48kph
  • Up to 12 hours to ensure lifting operations go uninterrupted
  • 4 independent thrusters spin up to 14,000 rpm in under a second

Removing the Jib of the WOLFF 355B at Chapter Living

Jib Removal

Our team visited the Chapter Living site in London during the dismantling of the WOLFFKRAN tower cranes. The WOLFF 355B jib had to be lifted and carefully lowered into the tight, space-constrained streets below. The Vita Load Navigator was deployed to ensure the operation was carried out with maximum safety and efficiency.

Alternative Solution:

Tag Lines

Issues:

Tight and constrained urban site with high winds

Vita Load Navigator