The P-GRID is a hybrid power unit that combines a 38 kVA Stage V Yanmar diesel generator with a lead-carbon battery bank and industrial inverters, delivering 160 kVA nominal output.
The battery handles peaks and light loads, so the generator runs far less than a conventional set sized for the same site.
It works on or off grid and in parallel with further units, from small sites to multi-crane developments.
Contact us to discuss your power requirement; our guide to site generators and hybrid battery systems covers the options in more detail.
For battery-only sites with a grid supply, see the Ampd Enertainer battery storage system.
View on this page or download.
Always read the manufacturer’s instructions before use. See the documents
A site generator sized for a tower crane’s peak spends most of its time running lightly loaded. The P-GRID instead stores energy in 34 x 12 V AGM lead-carbon batteries and supplies the site through eight Hercules CE+T three-phase inverters (pure sine wave, 400 V DC technology).
The 38 kVA generator starts only to recharge the batteries or support heavy demand, cutting fuel, emissions, noise and service hours.
It can also take a grid supply through a 63 A CE plug. Even a small 16 A or 32 A connection raises daily energy and peak capacity, as the table below shows.
Used this way it peak-shaves (covers short high demands from the battery) and can act as the core of a site microgrid.
| Configuration | Max energy per day | Peak, battery only (15 s) | Peak, battery + generator (15 s) |
|---|---|---|---|
| Stand alone | 480 kWh | 180 kVA | 200 kVA |
| 16 A external connection | 720 kWh | 200 kVA | 220 kVA |
| 32 A external connection | 960 kWh | 220 kVA | 240 kVA |
| 63 A external connection | 1,440 kWh | 240 kVA | 240 kVA |
For larger demands, units can run in parallel. Send us your load list and we will size the system.
A: The 160 kVA comes from the inverters and battery bank. The generator recharges the batteries and supports heavy demand, so it is sized for average load, not peak.
A: Yes. It takes a 400 V supply up to 63 A, which raises daily energy to as much as 1,440 kWh.
A: Yes. P-GRID units can run in parallel for larger sites.