This is an original data study. We took every battery energy storage (BESS) case study WOLFF Onsite has published for UK construction sites (six projects, from Glasgow to Shrewsbury, published between October 2024 and August 2026), pulled out every reported figure, and put them on a common footing: tonnes of CO2e per week, litres of diesel per week, and percentage change. We then checked the arithmetic, restated the carbon using the latest government conversion factors, and set the results against public data on generator fuel use, London's machinery emission rules, noise control and grid connections.
Where a case study did not report something, we say "not reported" and leave it blank. We have not filled gaps with estimates. Where we derive a number, we show how. If you want the background on how site batteries work and how to size one, read our complete guide to BESS for construction sites. This page is the evidence.
General information only. Site power design should be checked by a competent person, and equipment used in line with the manufacturer's instructions.
The quick answer
Across the six projects, battery energy storage was used to run tower cranes, hoists, aircraft warning lights and general site loads with either no generator at all (charged from a limited grid supply) or with a much smaller generator running a few hours a day. The published results are:
- 1,134 tonnes CO2e saved, as reported, across the four projects that published a total for their whole period (McGoff, VINCI, Prosperity at Smithfield Square, and GMI). Together those cover 168 weeks of operation.
- 3.1 to 13.4 tonnes CO2e saved per week once each total is divided by its own period. The spread reflects how much diesel each site would otherwise have burned, not how well the battery performed.
- 88% less diesel per week at South Clyde, Glasgow, where a battery plus a 100 kVA generator replaced a 550 kVA generator on one tower crane: 2,654 litres saved out of a 3,025-litre weekly baseline.
- 44% lower cost and 91% less CO2e at Smithfield Square, Birmingham, over five months on two tower cranes: £39,192 and 62.6 tonnes saved against a modelled diesel alternative.
- 30 A from a 90 A supply ran a lifting set-up at McGoff's Manchester site that had been planned around four generators totalling 1,120 kVA.
- Generator run time cut to about 25% of what was expected at GMI's Rochdale Road site, and to an average of 4.3 hours a day at Torsion's Burley Studios site in Leeds.
Three caveats matter. The diesel side of every comparison is a model or a plan, not a metered generator. The case studies use different carbon factors (2.51 and 2.65 kg CO2e per litre both appear). And one study, South Clyde, has been revised since first publication. We deal with each below.
How we built the dataset
The raw material is WOLFF Onsite's own published case studies, listed on our case studies page. We read each one in full in November 2026 and recorded every figure it gave: power requirement, plant replaced, supply size, generator size and run hours, fuel, carbon, cost, noise and duration. We then did four things.
1. Normalised to a common period
The projects ran for very different lengths of time: one week of reported savings at South Clyde, four weeks at GMI, twenty at Smithfield Square, 56 at McGoff and 88 at VINCI. Totals over different periods cannot be compared directly, so we divided each reported total by its reported period to get tonnes CO2e per week and, where litres were given, litres per week. Smithfield Square reports a five-month period (January to May 2026) and its diesel model uses a 20-week comparison period; we use 20 weeks.
2. Checked the arithmetic
Every total that could be recomputed from its own inputs was recomputed. Smithfield Square's figures reconcile exactly: 2 generators × 13 litres per hour × 50 hours a week × 20 weeks = 26,000 litres; 26,000 × £1.46 = £37,960; plus £50,400 of hire is £88,360. South Clyde's weekly saving of 2,654 litres is its 3,025-litre baseline less the 370.97 litres the hybrid generator used. Where figures did not reconcile, we say so in the project notes.
3. Restated carbon with current factors
The case studies used older or different conversion factors. We restated the carbon using the Department for Energy Security and Net Zero (DESNZ) 2026 greenhouse gas conversion factors, published in June 2026, so that the results can be compared with each other and with your own reporting.
4. Marked what is missing
No case study gave a measured noise level, and only three gave litres. We have not estimated these. Where we draw an inference (for example, the diesel volume a carbon figure implies), it is labelled as an inference and kept out of the headline numbers.
The six projects at a glance
Every project powered at least one tower crane. Between them they ran at least eight tower cranes, plus hoists, aircraft warning lights and general site power such as lighting, CCTV and turnstiles. Three set-ups were charged from a grid supply, and four used a small generator to recharge the battery at some point (VINCI did both, starting with a temporary generator and moving to a grid connection).
| Project | Location | What was powered | Plant the battery replaced or avoided | Set-up used |
|---|---|---|---|---|
| Careys, South Clyde Energy Centre | Glasgow | 1 × WOLFF 355 B tower crane; aircraft warning lights 24/7 on a flight path | 550 kVA generator (500 kVA in one section) plus a battery pack for the lights | Battery plus Stage 3 100 kVA generator (110 kVA in the disclaimer) |
| Torsion, Burley Studios | Leeds | WOLFF 320 FB tower crane; 485 kVA total requirement; 189-bed student scheme | 300 kVA generator with peak-shaving unit, plus a battery pack for warning lights | Battery plus Stage 3 110 kVA generator |
| McGoff Construction | Manchester | Cranes and hoists; 1,120 kVA total requirement | Four generators: 500, 300, 160 and 160 kVA | Battery on a 90 A low-voltage temporary building supply, drawing 30 A |
| VINCI Building, Royal Shrewsbury Hospital | Shrewsbury | 2 tower cranes; 460 kVA total requirement; aviation lights over Christmas | Not reported | Battery with small temporary generator, then grid connection |
| GMI Construction, Rochdale Road | Manchester | 1 tower crane, 3 hoists, lighting, CCTV, turnstile; 850 kVA total requirement | Not reported (generator run time compared with "initial expectations") | Battery with generator support |
| Prosperity Developments, Smithfield Square | Birmingham (Digbeth) | 2 × WOLFF 630B tower cranes; 2 aircraft warning lights; 305-apartment scheme | 2 × 250 kVA Stage V generators, 2 peak-shaving units, 2 light battery packs, 2 × 2,000-litre bowsers (modelled) | One battery on a limited three-phase low-voltage grid supply |
The "total power requirement" figures (460 to 1,120 kVA) describe the plant the site would have needed if everything were run from generators sized for peak demand. They are not the battery's rating. That gap, between what the plant could draw at peak and what it draws on average, is the reason a battery works on these sites, and we come back to it below.
Results: carbon saved
Five of the six projects published a carbon figure. Torsion's page carries headline counters for diesel, cost and carbon, but they show zero, so we treat Torsion's carbon as not reported.
| Project | Reported CO2e saved | Period | Per week (our calculation) | Reported % reduction | Factor used |
|---|---|---|---|---|---|
| McGoff, Manchester | 753 t | 56 weeks | 13.4 t | Not reported (no diesel used) | Not stated |
| GMI, Rochdale Road | 42 t | 4 weeks | 10.5 t | 70% | Not stated |
| Careys, South Clyde | 6.66 t | 7 days | 6.66 t | 88% (our calculation) | DEFRA 2023, 2.51 kg/L |
| VINCI, Shrewsbury | 276 t | 88 weeks | 3.1 t | Not reported | Not stated |
| Prosperity, Smithfield Square | 62.6 t | 20 weeks (Jan to May 2026) | 3.1 t | 91% | 2.65 kg/L diesel; 0.193 kg/kWh grid |
| Torsion, Burley Studios | Not reported | Not reported | Not reported | Not reported | DEFRA 2023 (stated) |
What drives the spread
The weekly saving ranges more than fourfold, from 3.1 to 13.4 tonnes. That is not a measure of battery performance. It mostly reflects the size of the diesel set-up being displaced and how long it would have run. McGoff had planned four generators totalling 1,120 kVA and ended up burning no diesel at all, so it shows the largest weekly saving. Smithfield Square's diesel model assumed generators running 50 hours a week at 25% load, which is a lighter baseline per crane. GMI's 10.5 tonnes a week comes from a short four-week period on a site with an 850 kVA requirement.
Grid-charged versus generator-assisted
The two fully grid-charged projects show the largest relative cuts: Smithfield Square reports 91%, and McGoff reports zero diesel. Generator-assisted sites report 70% (GMI) and 88% (South Clyde, our calculation from its fuel figures). That fits the physics: a grid-charged battery removes on-site combustion entirely, while a hybrid still burns some fuel to recharge. Six projects is too few to treat this as a rule, but the direction is consistent.
Implied diesel volumes
VINCI reported carbon but not litres. McGoff published a weekly figure (5,492 litres of diesel, £7,688 and 13 tonnes CO2e saved per 7 days) but no total. If you divide the carbon totals by the 2.51 kg CO2e per litre factor that two of the other case studies use, McGoff's 753 tonnes corresponds to exactly 300,000 litres and VINCI's 276 tonnes to about 110,000 litres. Round numbers like these suggest both totals were calculated from a diesel baseline at that factor. That is our inference, not a published figure, so we have not used these volumes anywhere else.
| Project | Reported CO2e | Implied litres at 2.51 kg/L (inference) | Implied litres per week |
|---|---|---|---|
| McGoff | 753 t | 300,000 L | about 5,360 L |
| VINCI | 276 t | about 110,000 L | about 1,250 L |
| GMI | 42 t | about 16,700 L | about 4,180 L |
Results: diesel, cost and run hours
Fuel, cost and run-hour data are patchier than carbon. Here is everything that was published.
| Project | Diesel | Cost | Generator run hours | Other savings |
|---|---|---|---|---|
| Careys, South Clyde | 2,654 L/week saved (3,025 L baseline; 370.97 L used) | £3,715.64/week fuel saving at £1.40/L | About 4 h/day on a 100 kVA generator, against a 550 kVA generator modelled at 55 h/week | £275/week battery-pack hire for warning lights avoided |
| Torsion, Burley Studios | Not reported | Not reported | 4.3 h/day average on a 110 kVA generator, mainly to recharge | £275/week warning-light battery hire avoided; no downtime during a 500-hour generator service |
| McGoff | None used; 5,492 L saved per 7 days (reported) | Not reported | None | Fewer fuel deliveries and less gate congestion |
| VINCI | Not reported | Not reported (described as cost effective) | Not reported | Fewer fuel deliveries |
| GMI | Not reported | 50% saving across the project | Reduced to about 25% of initial expectations | No noise complaints during silent hours |
| Prosperity, Smithfield Square | 26,000 L avoided over 20 weeks (1,300 L/week, modelled) | £39,192 saved (44%) | None on site; the diesel model assumed 50 h/week per generator | No downtime reported in the first seven months |
Two readings help here. First, GMI's "reduced to about 25% of initial expectations" means a cut of roughly 75% in generator hours, not a 25% cut. Second, the hybrid sites cut hours and engine size at the same time. At South Clyde a 100 kVA generator running about 28 hours a week replaced a 550 kVA generator modelled at 55 hours a week. Fewer hours on a much smaller engine is why the fuel saving (88%) is far bigger than the cut in hours alone would suggest.
A note on South Clyde's revision
The South Clyde study has been published in two versions. An earlier article reported savings of over 4,000 litres and about £5,640 a week, and 10.11 tonnes CO2e. That version gave no baseline; 10.11 t at 2.51 kg per litre is about 4,030 litres saved a week. The current case study, updated in November 2024 and based on 2.5 months of logged energy data, reports 2,654 litres, £3,715.64 and 6.66 tonnes against a 3,025-litre baseline. We use the current figures. Both versions are internally consistent at 2.51 kg per litre; the difference is the baseline. The current page also gives the original generator as 550 kVA in one section and 500 kVA in another, and the hybrid generator as 100 kVA and 110 kVA. Its weekly hybrid fuel figure (370.97 litres) is a little below what 14.1 litres per hour for 4 hours a day would give (394.8 litres); the page does not explain the difference.
Smithfield Square: the only full cost breakdown
The Smithfield Square case study is the most complete in the set. It publishes grid energy (monitored, with an estimate for a data gap in May) and electricity cost (January to March priced at the April tariff) for the battery side, and a fully itemised diesel model to compare against. That lets us test it.
| Item | Battery arrangement | Diesel model |
|---|---|---|
| Plant | 1 battery unit on limited grid supply | 2 × 250 kVA Stage V generators, 2 peak-shaving units, 2 warning-light battery packs, 2 × 2,000 L bowsers |
| Energy | 32,793.35 kWh imported from the grid | About 26,000 L diesel (13 L/h per generator at 25% load, 50 h/week, 20 weeks) |
| Energy cost | £12,168 | £37,960 (at £1.46/L) |
| Hire | £37,000 | £50,400 |
| Total | £49,168 | £88,360 |
| Carbon | About 6.3 t CO2e (0.193 kg/kWh) | About 68.9 t CO2e (2.65 kg/L) |
What the numbers say
- Hire alone decides it. The diesel kit's hire cost (£50,400) is higher than the whole battery arrangement including electricity (£49,168). The battery would have been cheaper even if the generators had run on free fuel.
- Electricity was not cheap. £12,168 for 32,793 kWh is about 37p per kWh all-in. The case study gives it as a single cost, so it may include standing or capacity charges that it does not break out. Either way, it is not a best-case tariff.
- Average crane demand was low. 32,793 kWh over 20 weeks is about 1,640 kWh a week for two cranes. If the cranes worked the 50 hours a week the diesel model assumes, that averages about 16 kW per crane. Two 630B cranes, each capable of drawing far more than that at peak, averaged a load you could run from a modest supply.
Stress-testing the diesel baseline
Here is where a careful reader should push. The diesel model assumes each 250 kVA generator burns 13 litres an hour at 25% load. But the metered energy suggests an average draw of about 16 kW per crane, which is closer to 8% of a 250 kVA generator's output (roughly 200 kW at a 0.8 power factor) than to 25%. At lower load a generator burns less fuel per hour, although it also gets less efficient per kWh. Manufacturers rarely publish fuel use below 25% load, so the true figure is uncertain.
So we halved the fuel. If the generators had burned 13,000 litres rather than 26,000, the diesel side would cost £69,380 and emit about 34.5 tonnes. The battery arrangement would still save £20,212 (29%) and 28.1 tonnes CO2e (82%). The conclusion holds even under a much less favourable baseline. The size of the saving is what moves.
Restated with DESNZ 2026 factors
Using the 2026 factors, 26,000 litres of average-blend diesel is 67.2 tonnes CO2e (26,000 × 2.58354 kg). The grid energy, including transmission and distribution losses, is 4.7 tonnes (32,793 × 0.14395 kg). The net saving is 62.5 tonnes, a 93% reduction, almost identical to the published 62.6 tonnes. The case study's grid factor (0.193) is higher than the 2026 figure, which makes the published battery-side carbon conservative.
Why tower cranes suit batteries: the load profile
All six projects share one feature: a tower crane. Cranes are close to the ideal load for a battery because they need a lot of power for very short periods and very little energy overall. WOLFF Onsite's BESS guide uses a sizing example with a peak of about 244 kW against an average of 10 to 15 kW. The Smithfield Square data above (about 16 kW per crane on average) sits right in that range.
What the battery does
A generator has to be sized for the peak, so it spends most of its life lightly loaded. A battery is sized differently. Its power rating must cover the peak, but its stored energy only needs to cover the gap between peak demand and what the supply or small generator can provide, for the few seconds or minutes of each lift. Between lifts, the supply tops it back up.
The manufacturer datasheet for the 10-foot battery unit used on several of these projects gives a continuous output of 475 A and a peak of 570 A for under a minute, at 380 to 400 V three-phase. That is roughly 330 kVA continuous at 400 V. Its maximum input is 90 A, which is exactly the size of the temporary building supply at McGoff, where the unit drew 30 A. At 400 V three-phase, 30 A is about 21 kVA, or less than 2% of the 1,120 kVA of generators originally planned for that site. (Both conversions are ours and assume a 400 V three-phase supply.)
Why limited grid supplies are the common thread
Two of the projects ran on grid supplies that could not have powered a tower crane directly: McGoff's 90 A temporary supply and Smithfield Square's "limited three-phase low-voltage" connection. VINCI's unit also moved onto a grid connection once one arrived, though the case study does not say how large that supply was. Getting a bigger supply is not quick. UK Power Networks, for example, says that for temporary supplies above 70 kVA it cannot give prices or timescales online, and requires full payment before work is booked. In November 2025 Ofgem said demand connection applications had risen sharply since November 2024, "far exceeding even the most ambitious forecasts". A battery lets a site use the supply it already has. At South Clyde the opposite happened: Careys had already paid for a grid connection for its second crane, so the battery ran only one.
The carbon behind a litre and a kilowatt-hour
Every carbon figure in this study is litres or kilowatt-hours multiplied by a conversion factor. The factor matters, and the case studies did not all use the same one.
The 2026 government factors
DESNZ publishes the UK's greenhouse gas conversion factors for company reporting each year. The 2026 set was first published on 11 June 2026. The figures relevant to site power are:
| Factor (DESNZ 2026) | Value | Scope |
|---|---|---|
| Diesel (average biofuel blend), per litre | 2.58354 kg CO2e | Scope 1 (burnt on site) |
| Diesel well-to-tank, per litre | 0.61101 kg CO2e | Scope 3 (extraction, refining, transport) |
| Gas oil, per litre | 2.75541 kg CO2e | Scope 1 |
| HVO (renewable diesel), per litre | 0.03558 kg CO2e | Scope 1; biogenic CO2 reported outside scopes |
| UK electricity generated, per kWh | 0.13096 kg CO2e | Scope 2 |
| UK electricity transmission and distribution losses, per kWh | 0.01299 kg CO2e | Scope 3 |
The grid factor fell by about 26% between the 2025 and 2026 sets, from 0.17700 to 0.13096 kg per kWh. DESNZ's major changes report attributes most of the fall to grid decarbonisation between 2023 and 2024, along with a new methodology and a shorter data lag. In practice this means a grid-charged battery's carbon footprint is now lower on paper than in any earlier year's reporting, before anything changes on site.
The factors the case studies used
- 2.51 kg per litre (DEFRA 2023): South Clyde and Torsion cite DEFRA 2023 without giving the number; South Clyde's figures match 2.51 kg per litre. The manufacturer datasheet states 2.51 explicitly.
- 2.65 kg per litre: Smithfield Square. This is close to the factor for 100% mineral diesel (no biofuel blend), which is higher than the forecourt average.
- Not stated: McGoff, VINCI and GMI.
Using 2.58354 instead of 2.51 adds about 3% to a diesel saving. South Clyde's 2,654 litres a week becomes 6.86 tonnes rather than 6.66. Using 2.65 instead of 2.58354 adds a further 2.6%. Neither changes any conclusion here, but if you are adding these figures to a carbon report, recalculate with the factor your organisation uses.
Per kilowatt-hour, the gap is wider
Comparing per litre hides the real difference, which is how much useful energy each litre delivers. The datasheet for a Cummins C100 D5 (a 100 kVA standby, 72 kW prime generator) lists 22 litres an hour at full prime load and 6 litres an hour at quarter load. That is about 3.3 kWh per litre at full load and 3.0 kWh per litre at 25% load, or 0.79 and 0.86 kg CO2e per kWh using the 2026 diesel factor. Grid electricity is 0.14 kg per kWh including network losses, about one-sixth of the figure for a well-loaded generator.
The Smithfield Square model implies something much worse. It assumes 26,000 litres to deliver work that took 32,793 kWh from the grid, or about 1.26 kWh per litre. That is about 2.05 kg CO2e per kWh. It reflects the reality of a generator sized for crane peaks spending most of its time lightly loaded, although, as the stress test above shows, the exact figure depends on fuel burn at very low load, which manufacturers do not publish.
Generators at low load: fuel and wet stacking
The case for a battery on a crane site rests on one point: a generator big enough for the peaks runs lightly loaded most of the time. Three pieces of public data show why that costs fuel and causes problems.
Fuel use does not fall in line with load
From the Cummins C100 D5 datasheet, fuel use at prime rating is:
| Load (prime, 72 kW) | Output | Fuel | kWh per litre | kg CO2e per kWh (2026 factor) |
|---|---|---|---|---|
| 25% | 18 kW | 6 L/h | 3.0 | 0.86 |
| 50% | 36 kW | 11 L/h | 3.3 | 0.79 |
| 75% | 54 kW | 16 L/h | 3.4 | 0.77 |
| 100% | 72 kW | 22 L/h | 3.3 | 0.79 |
Above 25% load the efficiency curve is fairly flat. The problem is what happens below it, and on a crane site that is where a peak-sized generator spends most of its hours. If average demand is around 15 kW, a 250 kVA generator is running at well under 10% of its capacity. Manufacturers do not publish fuel use at that point, but fuel per kWh rises because an engine burns fuel just to keep turning, however little power it delivers.
Wet stacking
Caterpillar's guidance on wet stacking says generator sets "operated at low loads (<30%) for extended periods of time" can develop it. Unburnt fuel and carbon collect in the exhaust and show as a black liquid leaking from exhaust joints. Caterpillar says this is "not usually an indication of an engine problem" in itself, but that "long periods of underloading, however, can lead to accelerated wear of components". On modern Stage V engines with diesel particulate filters, persistent light loading also makes it harder to keep the filter clean, which WOLFF Onsite's site power guide covers in more detail.
What the hybrid projects did about it
At South Clyde and Torsion, a 100 to 110 kVA generator replaced a 300 to 550 kVA one, and ran for about 4 to 4.3 hours a day, mainly to recharge the battery. When it runs, it runs at a useful load, then it switches off. The battery handles the light and peak loads in between. This is the mechanism behind the 88% fuel saving at South Clyde.
The rules pushing diesel off site
The case studies sit inside a regulatory picture that has been moving one way since 2022.
Red diesel, April 2022
From 1 April 2022 most construction users lost the right to use rebated "red" diesel. HMRC's Excise Notice 75 now limits it to specified uses such as agriculture, forestry, some sports grounds and heating or electricity generation for non-commercial premises. Construction plant and site generators must run on fully taxed white diesel. When the change took effect, red diesel carried 42.77 pence per litre less duty (10.18p against 52.95p), so the change raised the cost of every litre a site generator burns. HMRC also confirmed at the time that HVO and biodiesel would get no special duty treatment and are taxed at the same rate as road diesel.
Careys' Head of Sustainability is quoted in the South Clyde case study saying diesel makes up 95% of the company's Scope 1 and 2 emissions. That gives a sense of how much of a contractor's direct footprint sits in fuel.
London's NRMM Low Emission Zone
The Greater London Authority sets minimum engine emission standards for non-road mobile machinery (NRMM) rated 37 kW to 560 kW on construction sites. Constant-speed engines, which includes generators, must meet Stage V across all of London. From 1 January 2025 the minimum for other machinery rose to Stage IV across London. The GLA's published timetable then moves to Stage V throughout London from 1 January 2030, and to "only zero emission machinery" from 1 January 2040. Most sites must register in-scope machinery on the NRMM Register. Applying for an exemption to use an older Stage IIIA generator requires evidence, including what other technologies were considered, "including batteries where appropriate".
Noise: BS 5228
BS 5228 is the code of practice for noise and vibration control on construction and open sites. In England the 2014 version is approved under section 71 of the Control of Pollution Act 1974 by the Control of Noise (Code of Practice for Construction and Open Sites) (England) Order 2015. Local authorities must have regard to it when serving notices under section 60 of the 1974 Act, and courts must have regard to it when judging 'best practicable means' in noise nuisance cases under section 79 of the Environmental Protection Act 1990. In practice, site noise limits and working hours are set locally, and plant that runs overnight (such as a generator keeping crane warning lights on) is a common trigger for complaints.
None of the six case studies published a measured noise level. GMI reported zero noise complaints during silent hours, and the VINCI study highlights lower noise on a live hospital site. The manufacturer datasheet for the battery unit gives a sound pressure level of 57 to 61 dB(A) at 7 metres at full load. We have not found a like-for-like measured comparison for the generators these projects replaced, so we do not quote a ratio. For practical steps, see our guide on how to reduce generator noise on construction sites.
Industry targets
In June 2023 the Construction Leadership Council, through its CO2nstruct Zero programme, published a route map to reduce diesel use by non-road mobile machinery by 78% by 2035, in line with the UK's Sixth Carbon Budget. The CLC put the sector's NRMM fleet at about 300,000 items using about 2.5 million tonnes of oil equivalent of diesel a year. HS2 set its own target for all its sites to be diesel-free by 2029.
Worked examples: using these numbers on your own project
The examples below show how to turn your own figures into a carbon and cost comparison. They are illustrations, with the assumptions shown, not quotes.
Example 1: a generator-assisted crane (South Clyde method)
- Baseline fuel: take your planned generator's fuel use at its expected load and hours. South Clyde used 3,025 litres a week for a 550 kVA generator at 50% load for 55 hours.
- Hybrid fuel: smaller generator's litres per hour × hours per day × days. South Clyde reported 370.97 litres a week.
- Saving: 3,025 − 370.97 = 2,654 litres a week.
- Carbon: 2,654 × 2.58354 kg = 6.86 t CO2e a week (DESNZ 2026, Scope 1). Add 2,654 × 0.61101 kg = 1.62 t if you report well-to-tank.
- Cost: 2,654 × your diesel price. At the case study's £1.40 per litre that is £3,716 a week, before hire costs.
Example 2: a grid-charged battery (Smithfield Square method)
- Diesel side: generators × litres per hour × hours per week × weeks. Smithfield Square: 2 × 13 × 50 × 20 = 26,000 litres.
- Battery side: grid kWh. If you do not have metered data yet, a crane's average draw multiplied by working hours is a starting point. Smithfield Square averaged about 16 kW per crane over 50 hours a week.
- Carbon: 26,000 × 2.58354 = 67.2 t, less 32,793 × 0.14395 = 4.7 t, gives 62.5 t saved (93%).
- Cost: compare total hire plus energy on each side. Do not compare fuel against electricity alone; at Smithfield Square, hire was the larger part of both totals.
Example 3: an illustration for a single crane on a weak supply
Illustration only. Assumptions: one tower crane worked 50 hours a week for 40 weeks; generator alternative of one 250 kVA unit at Smithfield Square's modelled 13 litres an hour; battery charged from the grid at an average of 16 kW.
- Diesel: 13 × 50 × 40 = 26,000 litres, or 67.2 t CO2e at 2.58354 kg.
- Grid: 16 kW × 50 × 40 = 32,000 kWh, or 4.6 t CO2e at 0.14395 kg.
- Saving: about 62.6 t CO2e. If the generator actually burned half as much at its very low load, the saving would be about 29 t.
To check whether your loads suit a battery, our site power calculator sizes a set-up from your equipment list.
Checklist: what to record so your own results are citable
The gaps in this dataset are the most useful lesson. If you want your project's results to stand up in a carbon report or a tender, record these from day one:
- The diesel baseline you are comparing against: generator size, expected load, hours a week, and litres an hour from the manufacturer's datasheet.
- Whether the baseline is planned, modelled or metered. Say which.
- The conversion factor and its year (for example, DESNZ 2026, diesel average biofuel blend, 2.58354 kg per litre) and whether you include well-to-tank.
- Metered grid kWh, and the grid factor used for it, including or excluding transmission and distribution losses.
- Generator run hours and litres from the fuel log, if you run a hybrid.
- All hire costs on both sides: generators, peak-shaving units, warning-light battery packs, bowsers and the battery itself.
- Supply size in amps and the maximum the battery actually drew.
- The exact start and end dates of the comparison period.
- Noise measured at the site boundary, in dB(A) with distance, before and after, if noise is part of the case.
- Downtime and any interventions such as generator services.
Common mistakes when reading BESS performance data
- Comparing totals over different periods. 753 tonnes over 56 weeks and 42 tonnes over 4 weeks are not "big" and "small" results. Per week, they are 13.4 and 10.5 tonnes. Always normalise.
- Reading "reduced to 25%" as "reduced by 25%". GMI's generator hours fell to about a quarter of expectations, which is a 75% cut.
- Treating a modelled baseline as measured. Every diesel figure in these studies is a model or a plan. That is normal, because you cannot run both set-ups on the same site, but the assumptions (load, hours, litres per hour) should be stated and tested.
- Mixing conversion factors. 2.51, 2.58 and 2.65 kg per litre all appear in industry material. The difference is small (up to 6%) but it compounds across a portfolio.
- Ignoring the grid side. A grid-charged battery is not zero-carbon. At Smithfield Square the grid energy still accounted for about 6.3 tonnes on the case study's factor, about 9% of the diesel model's figure.
- Comparing fuel cost with electricity cost only. At Smithfield Square the generator, peak-shaver and bowser hire was larger than the fuel bill. Leave hire out and you misjudge the result.
- Quoting the "total power requirement" as the battery size. 460 to 1,120 kVA describes the peak-sized diesel plant, not the battery.
- Using sound power and sound pressure interchangeably. A dB(A) figure means little without knowing which it is and at what distance.
Frequently asked questions
Q: How much CO2e does a battery save on a construction site?
In these six UK projects, between 3.1 and 13.4 tonnes CO2e per week, depending on the diesel set-up it replaced. Over a full project the reported totals ranged from 42 tonnes (4 weeks) to 753 tonnes (56 weeks). The saving scales with the size and hours of the generators you would otherwise run.
Q: Can a battery run a tower crane from a small site supply?
In the projects studied, yes. At McGoff in Manchester a battery drawing 30 A from a 90 A temporary building supply ran lifting equipment planned around 1,120 kVA of generators. At Smithfield Square two WOLFF 630B cranes ran from a limited three-phase supply. The battery supplies the short lifting peaks and recharges between them.
Q: Is a battery cheaper than a generator?
At Smithfield Square, the only project with a full cost breakdown, the battery arrangement cost £49,168 over five months against a modelled £88,360 for diesel, a 44% saving. GMI reported a 50% cost saving. Results depend heavily on hire rates and fuel price, so compare whole hire-plus-energy costs for your own site.
Q: What conversion factor should I use for diesel in 2026?
The DESNZ 2026 factor for diesel (average biofuel blend) is 2.58354 kg CO2e per litre for direct emissions, with 0.61101 kg per litre well-to-tank if you report Scope 3 upstream emissions. Use the factor year your organisation reports against and state it.
Q: What is the grid electricity factor for 2026?
0.13096 kg CO2e per kWh generated, plus 0.01299 kg per kWh for transmission and distribution losses (DESNZ 2026). That is about 26% lower than the 2025 generation factor of 0.17700.
Q: Why do generators waste fuel on crane sites?
A generator must be sized for the crane's peak, which can be over 200 kW for a few seconds, while average demand is often 10 to 16 kW. The generator spends most of its time lightly loaded, where it delivers far less energy per litre. Caterpillar notes that running below 30% load for long periods can cause wet stacking.
Q: Does a hybrid battery and generator still save much fuel?
At South Clyde a battery with a 100 kVA generator running about 4 hours a day used 370.97 litres a week against a 3,025-litre baseline for a 550 kVA generator, an 88% saving. Torsion's 110 kVA generator averaged 4.3 hours a day, mainly to recharge.
Q: Do London's NRMM rules apply to batteries?
The GLA rules set emission standards for combustion engines from 37 kW to 560 kW. Generators must meet Stage V across London, and the GLA timetable moves to zero-emission machinery only from 1 January 2040. A battery has no engine, but any generator used to charge it must comply and be registered.
Q: How quiet is a site battery?
None of the case studies published measured noise levels. The manufacturer datasheet for the battery unit used on several projects gives 57 to 61 dB(A) at 7 metres at full load. GMI reported zero noise complaints during silent hours.
Q: Can I cite or reuse this data?
Yes. Please link to this page as the source. The infographic below can be embedded with the code provided. Where you quote a per-week figure or percentage, note that it is WOLFF Onsite's calculation on the published case-study figures.
Use this data and graphic
All figures on this page are free to cite with a link back. The infographic summarises the study in one image.
To talk through a battery for your own site, see our battery energy storage solutions page, browse battery energy storage systems, or contact us.

Use this graphic
Free to embed on your site, in training material or in a report. Copy the code below, which includes a credit link.
Sources
- WOLFF Onsite – How Prosperity Powered Two Tower Cranes From a Limited Grid Supply (case study, Aug 2026)
- WOLFF Onsite – Enertainer Cuts Noise, Cost & Carbon at GMI Construction's Rochdale Road Project (case study, Jan 2026)
- WOLFF Onsite – Enertainer Delivers 276T CO₂ Savings at VINCI Building (case study, Sep 2025)
- WOLFF Onsite – Grid-Powered Battery Energy Storage Eliminates Diesel at McGoff Site (case study, Aug 2025)
- WOLFF Onsite – Enertainer Powers Sustainable Torsion Project (case study, Jun 2025)
- WOLFF Onsite – Powering Tower Cranes with the Enertainer (case study, updated Nov 2024)
- WOLFF Onsite – Powering Tower Cranes with the Enertainer (earlier article version, Aug 2024)
- Manufacturer datasheet for the 10-ft battery unit (PDF hosted by WOLFF Onsite)
- DESNZ – Greenhouse gas reporting: conversion factors 2026 (published 11 June 2026)
- DESNZ – 2026 GHG conversion factors: major changes report
- DESNZ – 2026 GHG conversion factors: methodology report
- Cummins – C100 D5 generator set data sheet (fuel consumption)
- Caterpillar – Wet stacking prevention technologies for Cat 3500 diesel generator sets
- HMRC – Using rebated fuels in vehicles and machines (Excise Notice 75) from 1 April 2022
- Pinsent Masons Out-Law – UK restrictions on use of red diesel from 1 April 2022
- The Construction Index – HMRC confirms no relief for HVO (Nov 2021)
- Greater London Authority – Non-Road Mobile Machinery (NRMM)
- Construction Plant-hire Association – NRMM emission standards, London regions
- Explanatory memorandum to The Control of Noise (Code of Practice for Construction and Open Sites) (England) Order 2015, SI 2015/227
- BSI – BS 5228-1 Code of practice for noise and vibration control on construction and open sites. Noise
- Construction Industry Council – Diesel to disappear from most construction sites by 2035 under new plan (CLC, June 2023)
- UK Power Networks – Temporary connection: cost, time and what's involved
- Ofgem – Demand connections update (Nov 2025)